Sea Water Reverse Osmosis (SWRO) Plant Project at Jebel Ali Power Plant update – Dubai – United Arab Emirates

Construction of Dubai Electricity and Water Authority (DEWA)‘s Seawater Reverse Osmosis (SWRO) Desalination Plant at the Jebel Ali Power Plant and Desalination Complex is 79% complete and making significant progress.

Wherein the project’s main buildings are at the finishing stage. Most of the marine works are complete and the commissioning works started, especially after the successful operation of the first main power transformer.

The new SWRO plant and its associated facilities is being developed to include an advanced pre-treatment, double-pass reverse osmosis SWRO technology, post-treatment process and [
]

Sea Water Reverse Osmosis (SWRO) Plant Project at Jebel Ali Power Plant update – Dubai – United Arab Emirates2022-05-09T19:38:56+02:00

Acciona announces completion of Jebel Ali SWRO desalination plant – United Arab Emirates

Following achieving a major construction milestone, Acciona says that the Jebel Ali Sea Water Reverse Osmosis (SWRO) desalination plant is now producing water at 100% capacity. 

The desalination plant was built by Acciona and Besix and is owned by Dubai Electricity & Water Authority (DEWA).

According to a statement, the plant has begun its daily production of 182m liters of potable water and is already supplying the city’s water network.

(LINK).

Acciona announces completion of Jebel Ali SWRO desalination plant – United Arab Emirates2021-04-19T14:45:27+02:00

Saeed Mohammed Al Tayer reviews progress on SWRO-based desalination plant in Jebel Ali – Dubai

This plant is expected to be commissioned by May 2020 to meet the reserve margin criterion set for peak water demand for the year 2020 and beyond.

Dubai, UAE: HE Saeed Mohammed Al Tayer, MD & CEO of Dubai Electricity and Water Authority (DEWA), reviewed the progress on the sea water reverse osmosis (SWRO)-based desalination plant at the DEWA Jebel Ali Power & Desalination Complex.

This is one of the main complexes providing Dubai with reliable, efficient, and high-quality electricity and water [
]

Saeed Mohammed Al Tayer reviews progress on SWRO-based desalination plant in Jebel Ali – Dubai2019-02-21T13:33:37+01:00

Dubai Electricity and Water Authority (DEWA) has signed a 12-year Operating Plant Service Agreement (OPSA) with Siemens worth $463m (AED1.7bn)




The contract includes providing maintenance, spare parts and gas turbine rehabilitation for the second phase of K-Station at Jebel Ali Power and Desalination Station as well as for the third phase of H-Station at the Al Aweer Power Station.

DEWA has also extended the Long Term Maintenance Plan (LTMP) for seven more years for the second phase of L-Station.




(LINK)

Dubai Electricity and Water Authority (DEWA) has signed a 12-year Operating Plant Service Agreement (OPSA) with Siemens worth $463m (AED1.7bn)2017-06-06T12:22:39+02:00