Dubai Electricity and Water Authority (DEWA) has completed 96.50 percent of the Sea Water Reverse Osmosis (SWRO) desalination plant at Jebel Ali Power Plant and Water Desalination Complex.

The Complex is one of the key pillars for supplying Dubai with electricity and water services, adhering to the highest standards of availability, reliability, and quality.

DEWA had awarded the implementation of the AED897 million plant, with a production capacity of 40 million Imperial Gallons per Day (MIGD) of desalinated water, to a consortium led by Spain’s Acciona Agua and Belhasa Six Construct (BeSIX).

(LINK).