Repairs on gas turbine three (GT-3) of Oman’s Barka Two power and water desalisanation plant have finished ahead of schedule, nearly three weeks after an inspection initially revealed damage.

In an 11 April, 2019, filing to the Muscat Securities Market, plant operator SMN Power Holding said the affected unit returned to service on 4 April – six calendar days ahead of its previously communicated expected completion date.

The financial impact due to the outage and repair work amounted to $1.8m (OMR800,000), the group added.